Nine Mile Canyon Paving Project Update

image002.jpg

Nielson Construction paving crews are currently working between mileposts 38 and 39 near Gate Canyon.

Weather has delayed paving but crews resumed work on Tuesday, Sept. 30. The paving should be finished by Saturday, Oct. 3 if weather permits.

This week, additional crews will begin placing shoulder gravel and replacing delineators and signs. All shouldering, signs and cleanup work should be complete by the end of October.

There will be flagger operations controlling traffic during paving and travelers should expect 30-45 minute delays each direction. Please watch for haul trucks and additional workmen and equipment while traveling the canyon.